A condo renovation in South Florida runs on two sets of rules at once: the building's, enforced by the board and the manager, and the city's, enforced by the permit and inspections. Timing is confirmed in your written proposal. Expect a written application, a sound-rated underlayment for any hard floor, the contractor's license and insurance on file, weekday working hours, an elevator reservation and often a building damage deposit held by the association. J. Perry & Sons, a licensed renovation contractor near you, works in condo buildings across Broward and Palm Beach, and this is the checklist we run before pricing a unit.
The condo renovation checklist
| # | Item | Typical requirement | Who handles it |
|---|---|---|---|
| 1 | Alteration application | Scope, drawings, materials, schedule | Owner submits, contractor prepares |
| 2 | Board or committee approval | Timing is confirmed in your written proposal. | Owner |
| 3 | Contractor license and insurance | State CGC, liability COI naming the association, workers' comp | Contractor |
| 4 | Sound underlayment spec | IIC 50+ typical, data sheet attached | Contractor |
| 5 | Working hours | Usually 9 am–5 pm, Mon–Fri, no holidays | Both |
| 6 | Elevator reservation and padding | Booked by the day, protective pads | Contractor |
| 7 | Building damage deposit | Set by the association, refundable after walk-through | Owner |
| 8 | City or county permit | Plumbing, electrical, structural; not needed for same-layout flooring | Contractor |
| 9 | Water shut-off coordination | Advance notice to the building, as its rules require | Contractor |
| 10 | Debris and dust | Bagged debris, no dumpster on site without approval, floor protection in corridors | Contractor |
| 11 | Unit access and keys | Lockbox or doorman protocol | Owner |
| 12 | Final walk-through | Common areas inspected, building deposit released | Both |
Every building weights these differently. Boca Raton and Fort Lauderdale high-rises tend to be strict on elevators and hours; smaller garden-style buildings in Tamarac or Boynton Beach tend to be strict on noise and parking.
Condo Renovation Rules Start With the Alteration Application

Most condo renovation rules in South Florida are enforced through one document: the alteration application. A complete application gets reviewed. An incomplete one goes back to the owner, and the project waits. We prepare the contractor side of the package before we price the unit, so the board sees a clear scope the first time.
What a complete application usually includes: - A written scope of work, room by room, in plain language - A floor plan marked with the areas being changed - Product data sheets for the floor underlayment, the waterproofing membrane and any new windows or doors - Our Florida license, CGC1540699, and a certificate of insurance naming the association - Proof of workers' compensation coverage - The names of the licensed trades doing any plumbing, electrical or gas work - The permit number, or a note that the permit is pulled after approval
What slows approval down. Vague scopes ("remodel bathroom"), missing data sheets, an underlayment that does not meet the building's rating, and drawings that show a fixture moving across the slab. Each one sends the file back.
Who signs what. The owner signs and submits the application, because the owner is the member of the association. J. Perry & Sons prepares the scope, the data sheets and the insurance documents, and we answer the manager's questions directly so the owner is not relaying technical details.
Approval comes first. We do not start demolition, order building-specific materials or pull a permit until the association approves in writing. That protects you from a stop-work order from the board.
Our permits and compliance page explains how we handle the city side once the board signs off.
Next step: send us your building's renovation rules and the blank application form, and we will tell you exactly what goes in it.
Flooring: the rule that gets enforced most
Hard flooring over a neighbor's ceiling is the number one dispute in South Florida condos, so boards write specific rules:
- Minimum sound rating. Usually stated as IIC (impact) and sometimes STC (airborne), with 50 the common floor and some buildings asking for higher. The underlayment's data sheet has to show a tested assembly, not a marketing number.
- Underlayment type. After the project review, your written proposal lists the following scope and pricing: Cork, rubber or a cork-rubber mat at 2mm–6mm under tile, or an acoustic pad under floating floors. installed, on top of the for standard porcelain tile installed.
- Perimeter isolation. Some buildings require a foam strip at the walls so the tile does not touch the slab edge; it is cheap and it matters.
- Ground-floor exemptions. Many buildings waive the underlayment on the first floor over a garage or on grade. Ask; it saves money.
A floor installed without the specified underlayment can be ordered removed by the board. We install hard flooring in a condo once the association's spec is in hand. Our condo flooring rules guide covers the ratings in detail.
Free Project Review — call (561) 556-7509 or send us your project. Send the building's rules and a photo of the unit, and we'll contact you to set up your Free Project Review.
How We Build a Tile or Stone Floor to the Building's Sound Spec

Passing the sound rule on paper is one thing. Building the floor so it performs is another. These are the steps we follow on every hard floor in a condo.
Leveling first. Condo slabs are rarely flat. For tile and stone, we level with a sand-and-cement mortar mix, not a self-leveler. A flat base is what keeps large-format porcelain from cracking or showing lippage.
The underlayment goes down as tested. The data sheet shows a tested assembly: a slab thickness, an underlayment, a setting material and a tile. We match that assembly. Swapping the underlayment for a cheaper mat after approval is how owners end up with a removal order.
Perimeter isolation. A foam strip at every wall, column and cabinet base keeps the tile from touching the structure. Without it, footsteps bypass the underlayment and travel straight into the slab. Baseboards and the reglet detail are set so they do not bridge the gap.
Movement joints. Large tiled areas get soft joints in the field and at the perimeter. That protects the floor in summer heat and protects the neighbor below from a cracked, hollow floor.
Thresholds and doors. The new floor height is checked against the entry door, the balcony slider and the bathroom doors before tile is ordered, so doors are trimmed and thresholds planned instead of improvised.
See our condo flooring service, and the detailed guide to condo flooring rules and STC ratings. After the project review, your written proposal lists the following scope and pricing: Standard porcelain floors installed, with the underlayment as its own line.
Next step: send us the underlayment rating your building requires, and we will confirm the floor assembly before you choose tile.
Bathrooms and kitchens in a condo
- Plumbing stays in the stack. Drains cannot be moved through a slab in most buildings; sinks, showers and toilets stay close to where they are. A tub-to-shower conversion in the same spot is routine; moving the toilet across the room is usually not.
- Water shut-offs. A valve replacement needs the riser shut down, which affects the units above and below. The building schedules it, and the shut-off is planned in your written proposal.
- Waterproofing. Boards care about the unit below. A sheet or liquid membrane with a flood test on every shower, and some buildings require the flood test to be witnessed.
- Electrical. New circuits go through the unit's panel; the building's main is off limits.
- Ventilation. Exhaust fans tie into existing ducts. Range hoods are usually recirculating unless there is an existing exterior duct.
- Permits. Any of the above needs a city or county permit, which we pull after the board approves.
Protecting the Unit Below: Leaks, Flood Tests and Ceiling Repairs
In a condo, your bathroom sits on your neighbor's ceiling. Boards care about water more than any other risk, and so do we.
Waterproofing the whole wet area. A full shower gets a bonded membrane over the floor and up the walls, with the drain clamped or bonded to the membrane, not just a liner under the pan. The bathroom floor outside the shower is often waterproofed too, especially in older buildings.
The flood test. Before tile goes on, the shower floor is plugged and filled with water and checked against a marked line. If the building wants the test witnessed, we schedule it with the manager. After the project review, your written proposal lists the following scope and pricing: A full shower replacement, and a shower pan only. See our shower replacement page.
When a leak has already happened. If water from a unit above or from your own shower reached the unit below, the repair is more than a patch. We open the ceiling below, dry it, replace damaged framing where needed, then rebuild and finish the drywall. Plumbing repairs are done by licensed plumbers, coordinated and permitted by J. Perry & Sons, with the project staying under J. Perry & Sons. Our drywall repair page covers the ceiling work.
Valves and shut-offs. Old shut-off valves often fail when they are finally turned. We plan valve replacement with the building so the riser shut-off is done once and announced to the neighbors in advance.
Documentation. Photos of the membrane, the flood test and the drain connection go into the project file. Many boards ask for them, and they are worth keeping when you sell.
Next step: if a leak has already damaged a ceiling, send photos of both units and we will plan the repair and the rebuild together.
Balconies, windows and anything exterior
Balcony slabs, railings, windows and sliding doors are usually common elements or limited common elements. Tile on a balcony needs the board's approval, a weight check against the structural limit, and a waterproofing membrane that satisfies the building's engineer. Windows must match the building's approved product. Older coastal buildings going through milestone inspections may freeze this work entirely until the structural review is done. Our condo balcony tile guide goes deeper.
South Florida specifics
- Hours and noise. 9 am–5 pm weekdays is standard; some buildings start at 8 or stop at 4. Demolition is sometimes limited to specific days.
- Seasonal residents. Buildings in Boca Raton, Delray Beach and Palm Beach Gardens often restrict loud work from December to April when the building is full. Off-season work is often easier to schedule.
- Hurricane season. Material deliveries and balcony work pause during a storm watch; the building may require loose material to be moved indoors.
- Parking and loading. One or two contractor spaces, a loading dock with a schedule, and a cap on how many workers can be in the building.
- Insurance. Liability certificate naming the association, usually with a stated minimum, plus workers' comp. We carry both and send the certificate before the first day.
Renovating Your Condo While You Are Away
Many condo owners in Broward and Palm Beach are not in town for the whole project. A renovation can still run well, as long as access, decisions and updates are settled before work starts.
Access. The building decides how contractors get in: a lockbox, a key at the front desk, a doorman log or an escort to the unit. We register our crew with the manager, and only registered workers enter.
Decisions made up front. Tile, stone, fixtures, grout color and hardware are selected and approved before demolition, so nothing waits on a phone call. Samples can be brought to you before the proposal, or sent to you for sign-off. Once you sign the proposal, a simple rendering is included; detailed design by our in-house designer is billed separately.
Updates you can see. Photo updates at each stage: demolition, rough-in, waterproofing, flood test, tile and finish. Hidden work, such as membranes and valves, is photographed before it is covered.
Inspections. City inspections are scheduled by us and attended by our team. The manager is told in advance when an inspector needs access.
The final walk-through. The manager inspects the common areas, the elevator and the corridor. We repair anything our work touched before the building releases its damage deposit to you.
Our guide to renovating while you are away has more detail, and our HOA approval guide covers communities with a master association.
Next step: tell us when you will be out of town, and we will plan the selections and approvals before you leave. Your schedule is set out in the written proposal.
Timeline
The order of work in a condo is the same in every building: the alteration application and board approval, the city or county permit where one is needed, protection of the corridor and elevator, demolition, plumbing and electrical rough-in by licensed electricians and licensed plumbers, coordinated and permitted by J. Perry & Sons, inspections, waterproofing and flood tests, floor leveling and underlayment, tile and stone, fixtures and finish, then the final walk-through with the manager. Elevator bookings and the building's work rules shape the schedule. Your schedule is set out in the written proposal after the site review.
Condo renovation contractor by city
Free Project Review — call (561) 556-7509 or send us your project. Licensed Florida general contractor CGC1540699. Serving Broward, Palm Beach and Miami-Dade counties.
Related services
Condo renovation rules — FAQ
Do I need board approval to replace flooring in my condo?
Yes, in nearly every South Florida building, and the approval is based on the sound underlayment meeting the building's minimum rating.
What sound rating does a condo floor need?
Most buildings specify IIC 50 or higher; some require more. The underlayment data sheet must show a tested assembly that meets the number.
Can I move my bathroom or kitchen plumbing in a condo?
Within the same area, usually yes. Moving fixtures across the unit means cutting the slab and crossing the neighbor's ceiling, which most buildings prohibit.
What hours can contractors work in a condo?
Typically 9 am–5 pm on weekdays, no holidays, with some buildings limiting demolition days. The building's rules control.
How do I get an exact price?
Call (561) 556-7509 or send photos and rough dimensions through our project form. After the site review and scope confirmation, we prepare your itemized written proposal.
What goes into a condo alteration application?
A written scope, a floor plan, product data sheets for the underlayment and waterproofing, the contractor's license, a certificate of insurance naming the association and proof of workers' compensation. We prepare the contractor documents, and the owner signs and submits.
Can you start work before the board approves?
No. We wait for written approval from the association before demolition, ordering building-specific materials or pulling the permit. Starting early risks a stop-work order from the board.
Do you level a condo floor before tile?
Yes. For tile and stone we level with a sand-and-cement mortar mix, then install the approved underlayment and perimeter isolation as the building's tested assembly requires.
Who repairs the ceiling below if a shower leaks?
We do. We open the ceiling in the unit below, dry it, replace damaged framing where needed and rebuild the drywall and finish. Plumbing repairs are done by licensed plumbers, coordinated and permitted by J. Perry & Sons, with the project staying under J. Perry & Sons.
Can I renovate my condo while I am out of state?
Yes. Selections are approved before work starts, access is set up with the manager, and you get photo updates at each stage, including hidden work like membranes and valves.