Openings in Load-Bearing Block Walls: Widened Doorways, New Doors, Windows and Pass-Throughs in CMU

Wide new opening cut in a load-bearing concrete block wall between a kitchen and living room in South Florida.
FL CERTIFIED GC ·CGC1540699
150+Projects Completed
Free Project ReviewBook yours today
WorkmanshipWarranty

"There's a normal doorway between the kitchen and the living room, about three feet wide, in a block wall. We want it seven or eight feet wide so the two rooms feel connected. We don't want the whole wall gone, just a much bigger opening. Can you cut a concrete block wall like that without hurting the house?"

Yes. This is one of the most common structural jobs in a South Florida home, and it is done the same careful way every time.

Short answer: an opening in a load-bearing concrete block (CMU) wall is cut by holding up the structure above, saw-cutting the block, and then building new reinforced, solid-grouted jambs on each side so the wall can carry its load around the opening. In most homes the concrete bond beam at the top of the wall stays in place, and the engineer decides whether it can span the new opening as it is or needs a new lintel or reinforcement. A structural engineer designs the opening and seals the drawings. J. Perry & Sons builds it with its own block crew, pulls the permit and leaves the opening ready for drywall, stucco, a door or a window. Engineering and permit fees are separate from our price.

We work in homes across Broward, Palm Beach and Miami-Dade, with 150+ projects completed, and we build openings for builders and remodelers as well as homeowners. Licensed and insured. Certificate of insurance available on request. If you want the wall gone completely for an open plan, see load-bearing wall removal. All our structural services are under structural renovation.

Next step: measure the existing opening and the width you want, and take a photo of the wall from both sides.

Openings we build in block walls

Types of openings built in South Florida concrete block walls: doorways, pass-throughs and window-to-door conversions.

Widened doorways. A standard interior door opening enlarged to a wide cased opening between rooms. This is the job most homeowners call about: a three-foot doorway opened to seven feet or more so the kitchen, dining and living areas read as one space while the wall stays.

New interior openings. A new doorway where there was none, for a reworked layout, a new bedroom suite or a hall that connects two wings of the house.

Kitchen pass-throughs. A counter-height opening between the kitchen and a family room or patio, with a sill at counter height and the wall kept below and above.

New exterior doors. A new sliding door, French door or entry door cut into an exterior block wall. Converting an existing window into a door is covered on our window to sliding door conversion page.

New or larger windows. A window opening cut new or made wider or taller, for more light or a better view of the pool.

Arched openings made square. Reshaping an old arched opening into a clean rectangle is a stucco and masonry job we cover on squaring off arched openings.

Closing openings. An opening that is no longer wanted can be filled with block, tied into the existing wall and finished to match.

Next step: mark on a photo where the opening goes and how wide and tall you want it.

What the wall is doing, and why the bond beam matters

Most South Florida homes are built with concrete block walls that carry the roof and tie the house together against wind.

Block, cells and rebar. CMU walls are built of hollow concrete blocks. At corners, at the sides of openings and at set intervals, some of the hollow cells have vertical rebar and are filled solid with grout. Those reinforced cells are the columns hidden inside the wall.

The bond beam. At the top of the wall there is usually a continuous reinforced concrete beam, the bond beam or tie beam, poured into the top course and tying all the walls together. The roof framing is anchored to it. It is one of the most important parts of the house's structure.

Why we keep it. When an opening is enlarged, the goal is usually to work below the bond beam and leave it continuous. Cutting through it breaks the tie around the house, and that is a far bigger job that the engineer has to design specifically.

Can the bond beam span the new opening? Sometimes it can as it is, sometimes it needs added reinforcement, and sometimes a new lintel is needed under it. That is the engineer's call, based on the span, the load above and what the existing beam actually contains. We do not guess at what is inside a beam; the engineer may ask us to expose part of it so it can be checked.

Next step: if you have the original plans of the house, send them. They often show the bond beam and the filled cells.

How we build the opening

Five steps to cut a new opening in a load-bearing concrete block wall.

The steps below are the standard sequence. The details at each step come from the engineer's drawings.

1. Locate what is in the wall. Before any cut, we mark outlets, switches, pipes and ducts. Anything in the opening area is relocated by licensed electricians, licensed plumbers or licensed HVAC technicians, coordinated and permitted by J. Perry & Sons, with the project staying under J. Perry & Sons.

2. Protect the house. Floors are covered, the work area is sealed with plastic, and furniture is moved or wrapped. Cutting block makes dust and slurry, and the rest of the house should not see it.

3. Temporary shoring. Shores go up on both sides of the wall to carry the ceiling, roof framing or floor above while block is removed. The shoring stays until the new jambs and any lintel can carry the load.

4. Saw-cut the block. The outline of the new opening is cut with a concrete saw, wet to control dust, so the edges are straight and the surrounding block is not shattered. Then the block inside the cut is removed in pieces.

5. Build the jambs. At each side of the opening, the cut block cells are cleaned out, vertical rebar is set as the drawings show, often doweled into the slab with epoxy anchors, and the cells are filled solid with grout. These reinforced jambs are what carries the load beside the opening.

6. Lintel where required. If the engineer calls for it, a new precast or poured lintel, or added reinforcement at the bond beam, is installed before the shoring comes out.

7. Inspection. The building department inspects at the points it requires, usually before reinforcement is covered with grout or finish.

8. Shoring out, debris out. Once the new work can carry the load, shoring is removed and all debris is hauled away.

9. Ready for finish. The opening is left square and plumb, ready for drywall returns, stucco, a door frame or a window.

Next step: ask every contractor you talk to which of these steps are in their price. Shoring and grouted jambs are the two most often missing.

Lintels, jambs and shoring compared

Part What it does What to know
Bond beam Ties the walls together at the top and anchors the roof Kept continuous on most openings
Lintel Carries the wall above the opening Precast, poured or steel, sized by the engineer
Grouted jambs Carry the load down at each side Rebar set per drawings, cells filled solid
Shoring Holds the structure while the wall is open Temporary; stays until the new work can carry the load

Precast lintels are the standard concrete lintels used in Florida block construction and are set in the course above an opening. Poured lintels are formed and poured in place with rebar, useful when the opening size or the existing wall makes a precast piece impractical. Steel lintels appear in some designs for wide openings or tight clearances; ours are fabricated to the engineer's details and installed by our crew.

Next step: ask the engineer which lintel the design uses, so the proposal prices the right one.

Interior openings: doorways and pass-throughs

Width and height. A wider opening is usually the goal, but height matters too. Keeping the top of the opening below the bond beam sets the maximum height, and lining it up with door heads or a ceiling soffit in the same room makes it look planned.

The floor at the opening. Where a narrow doorway is widened, the floor under the old wall section is exposed. If the floors on both sides are different, or the old threshold leaves a seam, the best fix is to carry one floor through. See tile installation and flooring installation.

Finished returns. The new jambs are finished with drywall and corner bead, or with a clean square return. For a crisp, modern look we can finish the opening with no trim at all. Our drywall crew does the returns and the patch work around the opening.

Pass-throughs. The sill is built at the height the counter needs, and the wall below is kept solid. The pass-through is often finished with a stone or tile sill that matches the kitchen countertop.

Next step: decide whether you want a cased opening with trim or a clean drywall return. It changes the finish line in the proposal.

Exterior openings: doors and windows in South Florida

An exterior opening is a structural job and a wind-resistance job at the same time.

Wind zone. Miami-Dade and Broward are in the High-Velocity Hurricane Zone, and Palm Beach County is not, so the requirements for openings and products differ by county. The engineer's drawings and the product approvals set what is required.

Impact product. A new exterior opening gets an impact door or window installed to its approval. We install PGT, CGI, ES Windows and WinDoor products. Specialty openings such as oversized sliders, pocket or stacking sliders, pivot doors and corner glass are scopes we review from the drawings. See impact windows and doors.

Buck and anchoring. The opening is sized for the product, with the buck and anchoring the product approval and drawings require.

Stucco. The outside of the new opening is patched and finished to match the house. See stucco.

Next step: choose the door or window type before the engineer finalizes the opening size, so the rough opening fits the product.

Permits, the engineer and who does what

The engineer designs, we build. The structural engineer, hired by you or arranged by us, sets the opening size, the lintel or bond beam reinforcement, the jamb rebar and the anchors, and seals the drawings. J. Perry & Sons builds to them. If we find something in the wall the drawings did not show, we stop that part and get the engineer's direction in writing.

Permit. Cutting a new opening or enlarging one in a load-bearing wall needs a permit. J. Perry & Sons pulls it itself and follows every city and county requirement. See permits and compliance.

Scope Who does it
Opening design, lintel, jamb reinforcement Structural engineer
Permit J. Perry & Sons
Shoring, saw cutting, block removal, grouted jambs, lintel J. Perry & Sons
Steel lintel fabrication, where specified J. Perry & Sons
Electrical, plumbing, HVAC relocation Licensed electricians, licensed plumbers and licensed HVAC technicians (coordinated by J. Perry & Sons)
Drywall, stucco, doors, windows, floor tie-in J. Perry & Sons

For builders and remodelers. If you are running the job and need the block work only, we take the opening as a sub scope: shoring, cutting, jambs and lintel to your engineer's details, left ready for your finish trades. See our structural concrete construction services page.

Next step: send the engineer's detail if you have one; if not, we can arrange the engineer.

Starting price

After the project review, your written proposal lists the following scope and pricing: An opening in a load-bearing block wall. The final price is based on the width and height of the opening, whether a new lintel or bond beam reinforcement is needed, the shoring, what has to be relocated out of the wall, interior or exterior, and the finish you want at the opening. Engineering and permit fees are separate. We review every project personally and follow up with you directly.

To see how each factor affects the number, read what it costs to remove or open a load-bearing wall in Florida.

Next step: send your photos and measurements through our project form.

Openings by project type

Next step

Want a wider opening or a new door in a block wall? Send us a photo of the look you want and a photo of your house. We'll tell you what it's called, how we'd build it and the starting price. Builders and remodelers: send the drawings or the scope, and we'll price our trades and tell you what we need from your team.

Free Project Review. We look at your project with you and tell you what's possible and a starting price.

Call (561) 556-7509

By submitting, you agree that J. Perry & Sons may contact you by phone, text or email about your project.

Related services

Block wall opening FAQ

Can you widen a doorway in a concrete block wall?

Yes. The structure above is shored, the block is saw-cut to the new width, and new reinforced, solid-grouted jambs are built on each side to the engineer's drawings. In most homes the bond beam at the top of the wall stays in place.

Do I need an engineer to cut an opening in a block wall?

For a load-bearing wall, yes. The engineer designs the opening, the lintel or bond beam reinforcement and the jamb rebar, and seals the drawings for the permit. Engineering and permit fees are separate from our price.

Will cutting the block crack the rest of the wall?

A wet concrete saw makes a clean cut, and the block is removed in pieces inside the cut line, so the surrounding wall is not hammered apart. Shoring holds the load while the wall is open.

What is a bond beam and why does it matter?

It is the continuous reinforced concrete beam at the top of a block wall that ties the house together and anchors the roof. Openings are normally designed below it so it stays continuous.

Do I need a new lintel?

Sometimes. The engineer decides whether the existing bond beam can span the new opening as it is or needs a new lintel or added reinforcement.

What if there are pipes or wires in the wall?

They are relocated with the licensed specialty work coordinated by J. Perry & Sons before the opening is cut, with the project staying under J. Perry & Sons.

Can you cut a new exterior door into a block wall?

Yes. Exterior openings are designed for the structure and for the wind zone, and the new impact door or window is installed to its product approval. Stucco is patched to match the house.

Is J. Perry & Sons the engineer?

No. We are the licensed contractor and we build to the engineer's sealed drawings.