"We love the house and the lot, but we are out of room. We want a bigger primary suite, or a family room off the kitchen, or a bedroom for a parent who is moving in. We don't want to move. We want to know if it can be built, who draws it, who builds it, and how the new part will look like it was always there."

That is the conversation an addition starts with.

Short answer: a home addition in South Florida is usually a reinforced CMU block structure built on a new foundation and tied into the existing house. A licensed architect or engineer designs it, J. Perry & Sons pulls the permit and builds it to the sealed drawings, and one contract covers the whole job. Our own crews build the block walls, the openings into the existing house, the stucco, the drywall, the windows and doors, and the finishes. The slab and foundation, the roofing and the electrical, plumbing and HVAC are done by licensed trades, coordinated by J. Perry & Sons.

J. Perry & Sons is a licensed general contractor (CGC1540699) in Tamarac, serving Broward, Palm Beach and Miami-Dade. We have completed 150+ projects. Licensed and insured. Certificate of insurance available on request.

Next step: write down what the new space is for and roughly where on the lot you picture it. That is enough to start the review.

What kind of addition are you planning?

Primary suite additions. A larger bedroom, a walk-in closet and a new primary bathroom, often the most common addition on a single-story home. See bathroom renovation for how we build the bath inside it.

Family room or great room off the kitchen. The back wall of the house opens into a new room, so the kitchen and living space become one. This is where a new opening in the existing exterior block wall comes in. See block wall openings.

Bedroom and bath for a family member. A new bedroom with its own bath, sometimes with its own entry, for a parent, an adult child or guests.

Enclosing a covered patio. An existing covered area becomes conditioned living space with new block walls, impact windows and doors. Whether the existing slab and roof can stay is a question for the engineer.

Garage conversion and garage additions. The garage door opening is infilled with block and the space finished as a room, or a new garage is added to replace the one being converted.

Second-story additions. Building up instead of out is reviewed from the drawings. It starts with the engineer confirming the existing walls and foundation can carry the new floor, and the answer decides the project.

Next step: tell us which of these is closest to your plan and send a photo of the side of the house where the addition would go.

Can it be built? What decides it before anyone draws

Five things that decide whether a home addition can be built in South Florida: setbacks, lot coverage, flood zone, HOA review and existing structure.

Before design starts, a few things about your lot and your house decide what is possible. We go through them with you at the Free Project Review so you do not pay for drawings of something the city will not approve.

Setbacks and lot coverage. Every city sets how close a building can be to the property lines and how much of the lot can be covered. The architect checks the zoning for your property.

Flood zone. Many South Florida homes are in a flood zone. That can set the floor height of the addition, and on a large project the value of the work compared with the value of the house can trigger the rule that brings the whole house up to flood requirements. Read our guide to the flood zone 50 percent rule in Florida before you set the size.

HOA approval. If the home is in an HOA community, the association reviews the addition's size, roof, colors, windows and materials. We prepare what the HOA asks for alongside the permit. Our guide to HOA approval for renovations explains the process.

Easements and utilities. Septic systems, drain fields, utility lines and easements on the lot can limit where the addition can go.

The existing structure. Where the addition connects to the house, the existing wall, roof and foundation have to be reviewed by the engineer.

Next step: find your property survey and, if you have one, the original plans of the house. Both make the first conversation much more useful.

Who designs it and who builds it

This is the part homeowners most often find confusing, so here it is plainly.

The architect or engineer designs the addition. A licensed design professional draws the plans, sizes the foundation, the walls, the beams and the roof, and seals the drawings. If you already have one, we work with them. If you do not, we can arrange one for you, and their fee is separate from our price.

J. Perry & Sons builds it. We pull the permit in our name, build to the sealed drawings, coordinate the trades and licensed specialty contractors, schedule the inspections and close the permit. We are a builder, not an engineer or an architect. We do not stamp drawings or select the structural design. When something in the field does not match the drawings, we stop and ask the engineer.

Scope Who does it
Plans, structural design, sealed drawings Your architect or engineer (yours, or arranged by us)
Permit, inspections, closeout J. Perry & Sons
Site preparation and demolition J. Perry & Sons
Slab and foundation Licensed trades, coordinated by J. Perry & Sons
CMU block walls, reinforcing, lintels, tie beam J. Perry & Sons
New opening into the existing house J. Perry & Sons, to the engineer's design
Roof framing and roofing Licensed trades, coordinated by J. Perry & Sons
Electrical, plumbing, HVAC Licensed trades, coordinated by J. Perry & Sons
Impact windows and doors J. Perry & Sons
Stucco, drywall, tile, flooring, paint, finishes J. Perry & Sons

Engineering and permit fees are separate from our construction price, and they appear as their own lines.

Next step: if you already have an architect, send us their name and the drawings; if not, tell us and we will explain how we bring one in.

How a block addition is built

Six stages of building a reinforced block home addition in South Florida.

You do not need to know how to build an addition, but it helps to know what is happening on your property, so the inspections and the order of work make sense.

1. Layout and site preparation. The addition is staked from the survey and the drawings. Landscaping, pavers or concrete in the way are removed and the area is protected.

2. Foundation and slab. Licensed specialty contractors form and pour the footings and the slab, with the reinforcing and dowels the engineer details and the plumbing under the slab set before the pour, with the work coordinated by J. Perry & Sons. The footing and slab are inspected before concrete goes in.

3. Block walls. Our crew lays the CMU walls on the footing, with vertical reinforcing in the cells the engineer marks, solid grout around every bar, lintels over each window and door, and reinforced tie columns where they are drawn. For how we build new block, see masonry and CMU block walls.

4. Tie beam. A reinforced concrete beam runs along the top of the walls and ties them together, with the straps that will hold the roof set into it. The reinforcing is inspected before the pour.

5. Roof. The roof framing and the roofing go on through licensed trades, coordinated by J. Perry & Sons, tied to the straps in the tie beam as the drawings show, and the new roof is joined to the existing roof so water runs off the seam.

6. Opening into the house. Only once the addition is closed in do we open the existing exterior wall, so the house is never left open to the weather longer than it needs to be. The new opening is cut, shored and reinforced to the engineer's design.

7. Windows, doors, rough-ins and inspections. Impact windows and doors are installed in the new openings. Electrical, plumbing and HVAC rough-ins are performed by licensed electricians, licensed plumbers and a licensed HVAC contractor, coordinated by J. Perry & Sons, and are inspected before the walls close.

8. Finishes. Stucco outside, insulation as specified, drywall, tile, floors, trim and paint inside, then the final inspection and the permit is closed.

Next step: ask any contractor you interview to walk you through this order and tell you which steps are theirs and which go to partners.

Making the addition look like it was always there

A good addition is one nobody can pick out from the street. That comes from matching, and matching is planned before the walls go up.

Stucco texture and the seam. New stucco has to match the existing texture, and the joint between old and new walls is where a crack line forms if it is not detailed. We plan the transition and, where needed, refinish the existing wall so the whole elevation reads as one. See new construction stucco.

Floor heights. When flood rules allow it, the new floor is set to meet the existing floor, so there is no step at the opening. Where the addition has to sit higher, the drawings show how the transition is handled.

Floors that run through. Tile, stone or engineered wood can continue from the existing rooms into the addition, or the existing floor can be replaced so the whole area is one surface.

Windows and doors. New impact windows and doors are chosen to match the style and the frame color of the house. We install PGT, CGI, ES Windows and WinDoor. See impact windows and doors.

Roof lines and trim. Roof slopes, fascia, soffits and trim follow the existing house so the addition belongs to it.

Renderings and samples. We bring material samples to your home, and once you sign the proposal a simple rendering is included to give you an idea of the finished addition. A more detailed design is done by the designer on our team as a separate scope. See renderings and samples.

Next step: send photos of each side of the house so we can see the textures, windows and roof lines the addition has to match.

Permits and inspections on an addition

An addition always needs a permit, and it is a structural permit with several inspections.

We pull it. J. Perry & Sons pulls all permits itself, in its own name, and follows every city and county compliance requirement. The permit stays under J. Perry & Sons, including the work done by licensed specialty contractors, coordinated by J. Perry & Sons. Read why it matters who pulls the permit.

Inspections at each stage. Footing and slab, the reinforcing in the walls and the tie beam, roof, rough-ins, insulation and the final. Nothing is covered before it passes.

Hurricane requirements. Miami-Dade and Broward are in the High-Velocity Hurricane Zone, which carries stricter requirements for structure, roofs, windows and doors. Palm Beach County is not in the HVHZ, but it is still designed for high wind. Your engineer designs the addition for your location, and every window and door we install carries the product approval your location requires.

Notice of Commencement. On projects that require one, it is recorded before work starts, and we explain it to you first. See our guide to the Notice of Commencement in Florida.

For more on how we handle permits across the three counties, see permits and compliance.

Next step: ask us whether your city has any special requirements for additions, and we will check them in the review.

Price

We do not publish a starting price for home additions. Two additions of the same size can have very different costs, and a posted number would not help you plan. The price is based on the size and use of the space, the foundation the engineer designs for your soil and flood zone, the roof, the number of openings, the connection to the existing house, the bathrooms or kitchen inside it, and the finishes you choose.

Pricing is given in the itemized written proposal after the Free Project Review, once we have seen the lot, the house and the drawings. Each part of the work is its own line, including the work of licensed specialty contractors, with the work coordinated by J. Perry & Sons. Engineering and permit fees are separate.

Next step: send the survey, photos and any drawings you have, and we will review the project with you.

Additions and related work

For one company to run the whole project, see our general contractor page.

Next step

Send us a photo of the look you want and a photo of your house. We'll tell you what it's called, how we'd build it and the starting price.

Free Project Review. We look at your project with you and tell you what's possible and a starting price.

Call (561) 556-7509

By submitting, you agree that J. Perry & Sons may contact you by phone, text or email about your project.

Related services

Home addition FAQ

Do you design the addition?

No. A licensed architect or engineer designs the addition and seals the drawings. If you do not have one, we can arrange one for you, and their fee is separate. J. Perry & Sons builds to the drawings and pulls the permit.

Do you build the foundation and the roof?

The slab and foundation and the roofing are done by licensed trades, coordinated by J. Perry & Sons. You still have one contract and one company responsible. Our own crews build the block walls, the opening into the house, the windows and doors, the stucco and the finishes.

Will the addition match my house?

That is the goal from the start. We plan the stucco texture, the seam between old and new walls, the floor transition, the windows and the roof lines before construction, and we bring samples before you approve; once you sign the proposal, you see a simple rendering before materials are ordered.

Can I stay in the house during construction?

In most single-story additions, yes. The new structure is built and closed in before we open the existing wall, and the work area is separated and protected. The part of the house next to the opening is affected for part of the project, and we plan that with you.

Does my addition need a permit?

Yes. An addition always needs a building permit. We pull it in our name and schedule every inspection.

How much does a home addition cost?

We do not publish a starting price for additions because the foundation, roof, connection to the house and finishes change the cost too much from one home to the next. You receive an itemized written proposal after the Free Project Review. Engineering and permit fees are separate.

Can you convert my garage into a room?

Yes, where zoning and the HOA allow it. The garage door opening is infilled with block, the floor is brought to the right height, and the room gets windows, insulation, drywall, flooring and the electrical and HVAC work by licensed electricians and a licensed HVAC contractor, coordinated by J. Perry & Sons.

Do you also renovate the rest of the house?

Yes. Many addition projects include a kitchen, bathrooms or new floors in the existing house, and we price them in the same proposal.